How to Pause a Task in Desklog?

There are two ways to pause a task in Desklog:

Through Kanban View:

Step 1: From the Admin left panel, click on My Tasks. This will open up the Kanban View where all your tasks are listed into four sections: To Do, In Progress, Pause and Task Done.

Step 2: Drag and drop the task you wish to pause from In Progress to the section titled Pause. Your task will be paused.

Through Projects:

Step 1: From the Admin left panel, click on Projects and then Project List from the drop down. 

Step 2: From the list of projects, select the project containing the task you wish to pause. This will open up a page where all the tasks within the project are listed.

Step 3: Locate the task you wish to run and navigate to the section titled Status.

Step 4: Click the pause button to pause the task.