How to Set Estimated Cost to a Project?

Step 1: Click on Projects from the Admin left panel and from the drop down, click on Project List.

Step 2: From the list of projects, select the project you want to change the estimated cost of.

Step 3: Click on Settings in the page that opens.

Step 4: Locate the Basic Configuration section, then find the Estimated Amount subsection.

Step 5: Type in the amount you wish to set. Your new settings will be saved automatically.